Hydro Generation Scheduling: Comparison
Please note this is a comparison between Version 2 by Rita Xu and Version 1 by Salama A. Mostafa.

The optimal generation scheduling (OGS) of hydropower units holds an important position in electric power systems, which is significantly investigated as a research issue. Hydropower has a slight social and ecological effect when compared with other types of sustainable power source. The target of long-, mid-, and short-term hydro scheduling (LMSTHS) is to optimize the power generation schedule of the accessible hydropower units, which generate maximum energy by utilizing the available potential during a specific period. Numerous traditional optimization procedures are first presented for making a solution to the LMSTHS problem. Lately, various optimization approaches, which have been assigned as a procedure based on experiences, have been executed to get the optimal solution of the generation scheduling of hydro systems. This article offers a complete survey of the implementation of various methods to get the OGS of hydro systems by examining the executed methods from various perspectives. Optimal solutions obtained by a collection of meta-heuristic optimization methods for various experience cases are established, and the presented methods are compared according to the case study, limitation of parameters, optimization techniques, and consideration of the main goal. Previous studies are mostly focused on hydro scheduling that is based on a reservoir of hydropower plants. Future study aspects are also considered, which are presented as the key issue surrounding the LMSTHS problem.

 

 

The optimal generation scheduling (OGS) of hydropower units holds an important position in electric power systems, which is significantly investigated as a research issue. Hydropower has a slight social and ecological effect when compared with other types of sustainable power source. The target of long-, mid-, and short-term hydro scheduling (LMSTHS) is to optimize the power generation schedule of the accessible hydropower units, which generate maximum energy by utilizing the available potential during a specific period. Numerous traditional optimization procedures are first presented for making a solution to the LMSTHS problem. Lately, various optimization approaches, which have been assigned as a procedure based on experiences, have been executed to get the optimal solution of the generation scheduling of hydro systems. This article offers a complete survey of the implementation of various methods to get the OGS of hydro systems by examining the executed methods from various perspectives. Optimal solutions obtained by a collection of meta-heuristic optimization methods for various experience cases are established, and the presented methods are compared according to the case study, limitation of parameters, optimization techniques, and consideration of the main goal. Previous studies are mostly focused on hydro scheduling that is based on a reservoir of hydropower plants. Future study aspects are also considered, which are presented as the key issue surrounding the LMSTHS problem.

  • renewable energy
  • optimal generation scheduling
  • heuristic method
  • genetic algorithm
  • dynamic programming
  • hydropower generation
Please wait, diff process is still running!

References

  1. M. Nazari-Heris; B. Mohammadi-Ivatloo; G. B. Gharehpetian; Short-term scheduling of hydro-based power plants considering application of heuristic algorithms: A comprehensive review. Renewable and Sustainable Energy Reviews 2017, 74, 116-129, 10.1016/j.rser.2017.02.043.
  2. Jaber, S.; Chen, W.; Wang, K.; Li, J. Subcarrier Assignment and Power Allocation for SCMA Energy Efficiency. arXiv 2020, arXiv:2004.09960.
  3. Brekke, J.K. Medium-term Hydropower Scheduling with Provision of Capacity Reserves and Inertia. In Proceedings of the IEEE 2016 51st International Universities Power Engineering Conference (UPEC), Coimbra, Portugal, 6–9 September 2016; NTNU: Trondheim, Norway, 2016.
  4. N.A. Iliadis; Edgard Gnansounou; Development of the methodology for the evaluation of a hydro-pumped storage power plant: Swiss case study. Energy Strategy Reviews 2016, 9, 8-17, 10.1016/j.esr.2015.10.001.
  5. Xiao-Lin Ge; Li-Zi Zhang; Jun Shu; Nai-Fan Xu; Short-term hydropower optimal scheduling considering the optimization of water time delay. Electric Power Systems Research 2014, 110, 188-197, 10.1016/j.epsr.2014.01.015.
  6. J.P.S. Catalão; H.M.I. Pousinho; V.M.F. Mendes; Mixed-integer nonlinear approach for the optimal scheduling of a head-dependent hydro chain. Electric Power Systems Research 2010, 80, 935-942, 10.1016/j.epsr.2009.12.015.
  7. Joao P. S. Catalao; H.M.I. Pousinho; V.M.F. Mendes; Scheduling of head-dependent cascaded hydro systems: Mixed-integer quadratic programming approach. Energy Conversion and Management 2010, 51, 524-530, 10.1016/j.enconman.2009.10.017.
  8. Catalão, J.P.S.; Mariano, S.J.P.S.; Mendes, V.M.F.; Ferreira, L.A.F.M.; Scheduling of head-sensitive cascaded hydro systems: A nonlinear approach. IEEE Trans. Power Syst. 2008, 24, 337–346.
  9. M.M. Belsnes; Ove Wolfgang; Turid Follestad; E.K. Aasgård; Applying successive linear programming for stochastic short-term hydropower optimization. Electric Power Systems Research 2016, 130, 167-180, 10.1016/j.epsr.2015.08.020.
  10. Xiaolin Ge; Shu Xia; Wei-Jen Lee; C.Y. Chung; A successive approximation approach for short-term cascaded hydro scheduling with variable water flow delay. Electric Power Systems Research 2018, 154, 213-222, 10.1016/j.epsr.2017.08.034.
  11. Chao Ma; Jijian Lian; Junna Wang; Short-term optimal operation of Three-gorge and Gezhouba cascade hydropower stations in non-flood season with operation rules from data mining. Energy Conversion and Management 2013, 65, 616-627, 10.1016/j.enconman.2012.08.024.
  12. Li Mo; Peng Lu; Chao Wang; Jianzhong Zhou; Short-term hydro generation scheduling of Three Gorges–Gezhouba cascaded hydropower plants using hybrid MACS-ADE approach. Energy Conversion and Management 2013, 76, 260-273, 10.1016/j.enconman.2013.07.047.
  13. Arnel Glotic; Adnan Glotic; Peter Kitak; Jože Pihler; Igor Ticar; Parallel Self-Adaptive Differential Evolution Algorithm for Solving Short-Term Hydro Scheduling Problem. IEEE Transactions on Power Systems 2014, 29, 2347-2358, 10.1109/tpwrs.2014.2302033.
  14. Xiaohui Yuan; Yanbin Yuan; Yongchuan Zhang; A hybrid chaotic genetic algorithm for short-term hydro system scheduling. Mathematics and Computers in Simulation 2002, 59, 319-327, 10.1016/s0378-4754(01)00363-9.
  15. Jiang Chuanwen; Etorre Bompard; A self-adaptive chaotic particle swarm algorithm for short term hydroelectric system scheduling in deregulated environment. Energy Conversion and Management 2005, 46, 2689-2696, 10.1016/j.enconman.2005.01.002.
  16. Gang Li; Yongjun Sun; Yong He; Xiufeng Li; Qiyu Tu; Short-Term Power Generation Energy Forecasting Model for Small Hydropower Stations Using GA-SVM. Mathematical Problems in Engineering 2014, 2014, 381387, 10.1155/2014/381387.
  17. Jie Mu; Chao Ma; Jiaqing Zhao; Jijian Lian; Optimal operation rules of Three-gorge and Gezhouba cascade hydropower stations in flood season. Energy Conversion and Management 2015, 96, 159-174, 10.1016/j.enconman.2015.02.055.
  18. Sara Séguin; Pascal Côté; Charles Audet; Self-Scheduling Short-Term Unit Commitment and Loading Problem. IEEE Transactions on Power Systems 2015, 31, 133-142, 10.1109/tpwrs.2014.2383911.
  19. Liu Yuan; Jianzhong Zhou; Self-Optimization System Dynamics Simulation of Real-Time Short Term Cascade Hydropower System Considering Uncertainties. Water Resources Management 2017, 31, 2127-2140, 10.1007/s11269-017-1628-3.
  20. Changming Ji; Li Chuangang; Boquan Wang; Minghao Liu; Liping Wang; Multi-Stage Dynamic Programming Method for Short-Term Cascade Reservoirs Optimal Operation with Flow Attenuation. Water Resources Management 2017, 31, 4571-4586, 10.1007/s11269-017-1766-7.
  21. Wu Jiekang; Guo Zhuangzhi; Wu Fan; Short-term multi-objective optimization scheduling for cascaded hydroelectric plants with dynamic generation flow limit based on EMA and DEA. International Journal of Electrical Power & Energy Systems 2014, 57, 189-197, 10.1016/j.ijepes.2013.11.055.
  22. Xinyu Wu; Chuntian Cheng; Jian-Jian Shen; Bin Luo; Shengli Liao; Gang Li; A multi-objective short term hydropower scheduling model for peak shaving. International Journal of Electrical Power & Energy Systems 2015, 68, 278-293, 10.1016/j.ijepes.2014.12.004.
  23. Peng Lu; Jianzhong Zhou; Chao Wang; Qi Qiao; Li Mo; Short-term hydro generation scheduling of Xiluodu and Xiangjiaba cascade hydropower stations using improved binary-real coded bee colony optimization algorithm. Energy Conversion and Management 2015, 91, 19-31, 10.1016/j.enconman.2014.11.036.
  24. Alexia Marchand; Michel Gendreau; Marko Blais; Gregory Emiel; Fast Near-Optimal Heuristic for the Short-Term Hydro-Generation Planning Problem. IEEE Transactions on Power Systems 2017, 33, 227-235, 10.1109/tpwrs.2017.2696438.
  25. Ellen Krohn Aasgård; Christian Øyn Naversen; Marte Fodstad; Hans Ivar Skjelbred; Optimizing day-ahead bid curves in hydropower production. Energy Systems 2017, 9, 257-275, 10.1007/s12667-017-0234-z.
  26. R. Naresh; J. Sharma; Short term hydro scheduling using two-phase neural network. International Journal of Electrical Power & Energy Systems 2002, 24, 583-590, 10.1016/s0142-0615(01)00069-2.
  27. Bin Xu; Ping-An Zhong; Zachary Stanko; Yunfa Zhao; William W.-G. Yeh; A multiobjective short-term optimal operation model for a cascade system of reservoirs considering the impact on long-term energy production. Water Resources Research 2015, 51, 3353-3369, 10.1002/2014wr015964.
  28. Castro, M.S.; Sousa, J.; Saraiva, J. Hydro scheduling optimization considering the impact on market prices and head drop using the linprog function of MATLAB®. In Proceedings of the 2017 IEEE Manchester PowerTech, Manchester, UK, 18–22 June 2017.
  29. Mengfei Xie; Jianzhong Zhou; Chunlong Li; Peng Lu; Daily Generation Scheduling of Cascade Hydro Plants Considering Peak Shaving Constraints. Journal of Water Resources Planning and Management 2016, 142, 04015072, 10.1061/(asce)wr.1943-5452.0000622.
  30. Xiaohui Yuan; Yongchuan Zhang; Liang Wang; Yanbin Yuan; An enhanced differential evolution algorithm for daily optimal hydro generation scheduling. Computers & Mathematics with Applications 2008, 55, 2458-2468, 10.1016/j.camwa.2007.08.040.
  31. Xiaohui Yuan; Liang Wang; Yanbin Yuan; Application of enhanced PSO approach to optimal scheduling of hydro system. Energy Conversion and Management 2008, 49, 2966-2972, 10.1016/j.enconman.2008.06.017.
  32. Sinvaldo Rodrigues Moreno; Eloy Kaviski; DAILY SCHEDULING OF SMALL HYDRO POWER PLANTS DISPATCH WITH MODIFIED PARTICLES SWARM OPTIMIZATION. Pesquisa Operacional 2015, 35, 25-37, 10.1590/0101-7438.2015.035.01.0025.
  33. G.B. Shrestha; B.K. Pokharel; T.T. Lie; S.-E. Fleten; Medium Term Power Planning With Bilateral Contracts. IEEE Transactions on Power Systems 2005, 20, 627-633, 10.1109/tpwrs.2005.846239.
  34. Costas G. Baslis; Anastasios G. Bakirtzis; Mid-Term Stochastic Scheduling of a Price-Maker Hydro Producer With Pumped Storage. IEEE Transactions on Power Systems 2011, 26, 1856-1865, 10.1109/tpwrs.2011.2119335.
  35. Joao P. S. Catalao; H.M.I. Pousinho; J. Contreras; Optimal hydro scheduling and offering strategies considering price uncertainty and risk management. Energy 2012, 37, 237-244, 10.1016/j.energy.2011.11.041.
  36. Flatabø, N.; Haugstad, A.; Mo, B.; Fosso, O.B. Short-term and medium-term generation scheduling in the Norwegian hydro system under a competitive power market structure. In Proceedings of the EPSOM’98 (International Conference on Electrical Power System Operation and Management), ETH Zürich, Switzerland, 23–25 September 1998.
  37. Abgottspon, H.; Bucher, M.; Andersson, G. Stochastic dynamic programming for unified short-and medium-term planning of hydro power considering market products. In Proceedings of the 12th IEEE International Conference on Probabilistic Methods Applied to Power Systems (PMAPS), Istanbul, Turkey, 10–14 June 2012.
  38. Abgottspon, H.; Andersson, G. Approach of integrating ancillary services into a medium-term hydro optimization. In Proceedings of the XII SEPOPE: Symposium of Specialists in Electric Operational and Expansion Planning, Zurich, Switzerland, 20–23 May 2012.
  39. Abgottspon, H.; Njálsson, K.; Bucher, M.A.; Andersson, G. Risk-averse medium-term hydro optimization considering provision of spinning reserves. In Proceedings of the IEEE 2014 International Conference on Probabilistic Methods Applied to Power Systems, Durham, UK, 7–10 July 2014; pp. 1–6.
  40. Arild Helseth; Marte Fodstad; Birger Mo; Optimal Medium-Term Hydropower Scheduling Considering Energy and Reserve Capacity Markets. IEEE Transactions on Sustainable Energy 2016, 7, 934-942, 10.1109/tste.2015.2509447.
  41. Martin N. Hjelmeland; Arild Helseth; Magnus Korpås; A Case Study on Medium-Term Hydropower Scheduling with Sales of Capacity. Energy Procedia 2016, 87, 124-131, 10.1016/j.egypro.2015.12.341.
  42. Aquino, R.R.; Carvalho, M.A.; Neto, O.N.; Lira, M.M.; de Almeida, G.J.; Tiburcio, S.N. Recurrent neural networks solving a real large scale mid-term scheduling for power plants. In Proceedings of the IEEE the 2010 International Joint Conference on Neural Networks (IJCNN), Barcelona, Spain, 18–23 July 2010; pp. 1–6.
  43. Aquino, R.R.; Neto, O.N.; Lira, M.M.; Carvalho, M.A. Solving a real large scale mid-term scheduling for power plants via hybrid intelligent neural networks systems. In Proceedings of the IEEE 2011 International Joint Conference on Neural Networks, San Jose, CA, USA, 31 July–5 August 2011; pp. 785–792.
  44. M.M. Lotfi; S.F. Ghaderi; Possibilistic programming approach for mid-term electric power planning in deregulated markets. International Journal of Electrical Power & Energy Systems 2012, 34, 161-170, 10.1016/j.ijepes.2011.10.014.
  45. Yanjia Zhao; Xi Chen; Qing-Shan Jia; Xiaohong Guan; Shuanghu Zhang; Yunzhong Jiang; Long-Term Scheduling for Cascaded Hydro Energy Systems With Annual Water Consumption and Release Constraints. IEEE Transactions on Automation Science and Engineering 2010, 7, 969-976, 10.1109/TASE.2010.2050139.
  46. Scarcelli, R.O.; Zambelli, M.S.; Filho, S.; Carneiro, A.A. Aggregated inflows on stochastic dynamic programming for long term hydropower scheduling. In Proceedings of the IEEE 2014 North American Power Symposium, Pullman, WA, USA, 7–9 September 2014; pp. 1–6.
  47. R.O.C. Scarcelli; M.S. Zambelli; S. Soares; A.A.F.M. Carneiro; Ensemble of Markovian stochastic dynamic programming models in different time scales for long term hydropower scheduling. Electric Power Systems Research 2017, 150, 129-136, 10.1016/j.epsr.2017.05.013.
  48. B. Mo; A. Gjelsvik; A. Grundt; Integrated risk management of hydro power scheduling and contract management. IEEE Transactions on Power Systems 2001, 16, 216-221, 10.1109/59.918289.
  49. Mo, B.; Gjelsvik, A.; Grundt, A.; Karesen, K. Optimisation of hydropower operation in a liberalised market with focus on price modelling. In Proceedings of the 2001 IEEE Porto Power Tech Proceedings, Porto, Portugal, 10–13 September 2001; p. 6.
  50. L Hongling; J Chuanwen; Z Yan; A review on risk-constrained hydropower scheduling in deregulated power market. Renewable and Sustainable Energy Reviews 2008, 12, 1465-1475, 10.1016/j.rser.2007.01.018.
  51. Larsen, C.T.; Doorman, G.L.; Mo, B. Evaluation of scenario reduction methods for stochastic inflow in hydro scheduling models. In Proceedings of the 2015 IEEE Eindhoven PowerTech, Eindhoven, The Netherlands, 29 June–2 July 2015.
  52. Hjelmeland, M.N.; Korpås, M.; Helseth, A. Combined SDDP and simulator model for hydropower scheduling with sales of capacity. In Proceedings of the IEEE 2016 13th International Conference on the European Energy Market, Porto, Portugal, 6–9 June 2016.
  53. Baohong Lu; Kunpeng Li; Hanwen Zhang; Wei Wang; Huanghe Gu; Study on the optimal hydropower generation of Zhelin reservoir. Journal of Hydro-environment Research 2013, 7, 270-278, 10.1016/j.jher.2013.01.002.
  54. Mengfei Xie; Jianzhong Zhou; Chunlong Li; Shuang Zhu; Long-term generation scheduling of Xiluodu and Xiangjiaba cascade hydro plants considering monthly streamflow forecasting error. Energy Conversion and Management 2015, 105, 368-376, 10.1016/j.enconman.2015.08.009.
  55. Chun-Tian Cheng; Wen-Chuan Wang; Dong-Mei Xu; K. W. Chau; Optimizing Hydropower Reservoir Operation Using Hybrid Genetic Algorithm and Chaos. Water Resources Management 2007, 22, 895-909, 10.1007/s11269-007-9200-1.
  56. Yaoyao He; Jianzhong Zhou; Xiu-Qiao Xiang; Heng Chen; Hui Qin; Comparison of different chaotic maps in particle swarm optimization algorithm for long-term cascaded hydroelectric system scheduling. Chaos, Solitons & Fractals 2009, 42, 3169-3176, 10.1016/j.chaos.2009.04.019.
  57. Hammid, A.T.; Sulaiman, M.H. Optimal Long-Term Hydro Generation Scheduling of Small Hydropower Plant (SHP) using Metaheuristic Algorithm in Himreen Lake Dam. In Proceedings of the MATEC Web of Conferences, Kuala Lumpur, Malaysia, 28–30 November 2017.
  58. Ali Thaeer Hammid; Mohd Herwan Bin Sulaiman; Series division method based on PSO and FA to optimize Long-Term Hydro Generation Scheduling. Sustainable Energy Technologies and Assessments 2018, 29, 106-118, 10.1016/j.seta.2018.06.001.
  59. Sheng-Li Liao; Benxi Liu; Chun-Tian Cheng; Zhi-Fu Li; Xin-Yu Wu; Long-Term Generation Scheduling of Hydropower System Using Multi-Core Parallelization of Particle Swarm Optimization. Water Resources Management 2017, 28, 3391-2807, 10.1007/s11269-017-1662-1.
  60. Huifeng Zhang; Jianzhong Zhou; Na Fang; Rui Zhang; Yongchuan Zhang; An efficient multi-objective adaptive differential evolution with chaotic neuron network and its application on long-term hydropower operation with considering ecological environment problem. International Journal of Electrical Power & Energy Systems 2013, 45, 60-70, 10.1016/j.ijepes.2012.08.069.
  61. Chao Wang; Jianzhong Zhou; Peng Lu; Liu Yuan; Long-term scheduling of large cascade hydropower stations in Jinsha River, China. Energy Conversion and Management 2015, 90, 476-487, 10.1016/j.enconman.2014.11.024.
  62. Xiang Liao; Jianzhong Zhou; Rui Zhang; Yongchuan Zhang; An adaptive artificial bee colony algorithm for long-term economic dispatch in cascaded hydropower systems. International Journal of Electrical Power & Energy Systems 2012, 43, 1340-1345, 10.1016/j.ijepes.2012.04.009.
  63. Liao, X.; Zhou, J.; Ouyang, S.; Zhang, R.; Zhang, Y.; Multi-objective artificial bee colony algorithm for long-term scheduling of hydropower system: A case study of china. Water Util. J. 2014, 7, 13–23.
  64. Monica S. Zambelli; Ivette Luna; Secundino Soares; Predictive Control Approach for Long-Term Hydropower Scheduling Using Annual Inflow Forecasting Model. IFAC Proceedings Volumes 2009, 42, 191-196, 10.3182/20090705-4-sf-2005.00035.
  65. Zambelli, M.S.; Luna, I.; Soares, S. Long-term hydropower scheduling based on deterministic non-linear optimization and annual inflow forecasting models. In Proceedings of the 2009 IEEE Bucharest PowerTech, Bucharest, Romania, 28 June–2 July 2009; pp. 1–8.
  66. Monica S. Zambelli; Secundino Soares Filho; André Emilio Toscano; Erinaldo Dos Santos; Donato Da Silva Filho; NEWAVE versus ODIN: comparison of stochastic and deterministic models for the long term hydropower scheduling of the interconnected brazilian system. Sba: Controle & Automação Sociedade Brasileira de Automatica 2011, 22, 598-609, 10.1590/s0103-17592011000600005.
  67. Mantawy, A.; Soliman, S.; El-Hawary, M. A new tabu search algorithm for the long-term hydro scheduling problem. In Proceedings of the IEEE Power Engineering 2002 Large Engineering Systems Conference on LESCOPE 02, Halifax, NS, Canada, 26–28 June 2002.
  68. A.H. Mantawy; S.A. Soliman; M.E. El-Hawary; The long-term hydro-scheduling problem—a new algorithm. Electric Power Systems Research 2003, 64, 67-72, 10.1016/s0378-7796(02)00146-3.
  69. N. Nabona; Multicommodity network flow model for long-term hydro-generation optimization. IEEE Transactions on Power Systems 1993, 8, 395-404, 10.1109/59.260847.
  70. Fosso, O.B.; Gjelsvik, A.; Haugstad, A.; Mo, B.; Wangensteen, I. Generation scheduling in a deregulated system. The Norwegian case. IEEE Trans. Power Syst. 1999, 14, 75–81.
  71. Fleten, S.E.; Haugstvedt, D.; Steinsbø, J.A.; Belsnes, M.; Fleischmann, F. Bidding Hydropower Generation: Integrating Short-and Long-Term Scheduling; University Library of Munich: Munich, Germany, 2011.
  72. Grønvik, I.; Hadziomerovic, A.; Ingvoldstad, N.; Egging, R.; Fleten, S.E. Feasibility of linear decision rules for hydropower scheduling. In Proceedings of the IEEE 2014 International Conference on Probabilistic Methods Applied to Power Systems (PMAPS), Durham, UK, 7–10 July 2014; pp. 1–6.
  73. Guisández, I.; Pérez-Díaz, J.; Wilhelmi, J. Effects of the maximum flow ramping rates on the long-term operation decisions of a hydropower plant. In Proceedings of the International Conference on Renewable Energies and Power Quality, Córdoba, Spain, 7–10 April 2014.
  74. Ge, X.; Zhong, J.; Xia, S. Long-term scheduling with the consideration of interruptible load. In Proceedings of the 2016 IEEE International Conference on Power and Renewable Energy (ICPRE), Shanghai, China, 21–23 October 2016.
  75. Sharma, R.N.; Chand, N.; Sharma, V.; Yadav, D. Decision support system for operation, scheduling and optimization of hydro power plant in Jammu and Kashmir region. Renew. Sustain. Energy Rev. 2015, 43, 1099–1113.
  76. Zhao, T.; Zhao, J.; Liu, P.; Lei, X. Evaluating the marginal utility principle for long-term hydropower scheduling. Energy Convers. Manag. 2015, 106, 213–223.
  77. Xiomara, B.; Soares, S. Accuracy assessment of the long-term hydro simulation model used in Brazil based on post-operation data. In Proceedings of the IEEE 2017 6th International Conference on Clean Electrical Power (ICCEP), Santa Margherita Ligure, Italy, 27–29 June 2017.
More